Installation and Servicing
Instructions
Alpha InTec 12S, 18S, 28S
Range of Wall Mounted, Fan Assisted, Room Sealed,
Gas Fired, High Efficiency Condensing System Boilers
Nepicar House, London Road,
Wrotham Heath, Sevenoaks,
Kent TN15 7RS
For Technical help or for Service call ...
ALPHA HELPLINE Tel: 0844 871 8764
website: www.alpha-innovation.co.uk
Alpha InTec 12S (NG) G.C. No. 41 532 22
Alpha InTec 18S (NG) G.C. No. 41 532 23
Alpha InTec 28S (NG) G.C. No. 41 532 24
Alpha InTec 12S (LPG) G.C. No. 41 532 25
Alpha InTec 18S (LPG) G.C. No. 41 532 26
Alpha InTec 28S (LPG) G.C. No. 41 532 27
For use with Natural Gas or Propane Gas (AS SUPPLIED)
Leave these instructions with the User
0051
Page view 0
1 2 3 4 5 6 ... 43 44

Summary of Contents

Page 1 - Alpha InTec 12S, 18S, 28S

Installation and ServicingInstructionsAlpha InTec 12S, 18S, 28SRange of Wall Mounted, Fan Assisted, Room Sealed,Gas Fired, High Efficiency Condensing S

Page 2 - BENCHMARK SCHEME

103.5 FLUE TERMINAL LOCATION - Figs. 4 and 5Alpha InTec S - General Boiler InformationA Directly below an opening, air brick, windows, etc.B Below

Page 3 - 1 INTRODUCTION

113.6 BOILER LOCATIONThe boiler is not suitable for external installation unless it is installed within a purpose designed weatherproof building.The

Page 4 - 2 TECHNICAL DATA

123.7 CENTRAL HEATING SYSTEM - Fig. 6The boiler is designed for use in a sealed central heating system in accordance with the requirements of BS EN 1

Page 5 - 2.3 PHYSICAL DATA

13Alpha InTec S - General Boiler Information3.9 FLUSHING THE HEATING SYSTEMIt is essential that the central heating system is thoroughly cleaned and

Page 6 - 2.4 FLUE LENGTHS

14Alpha InTec S - General Boiler InformationFig. 9 - External soakawayFig. 8 - External gullyOpen end of pipediverted into gullybelow grid but abovewa

Page 7 - 2.7 BOILER SCHEMATIC

154.3 PREPARE THE WALL - Fig. 11If the optional wall jig is used refer to the instructions supplied with the kit.1. Decide upon the position of the

Page 8 - 3 GENERAL BOILER INFORMATION

164. Cut the 110 mm diameter hole (or use a 107 mm core drill) in the wall for the flue. Notes: 1. Ensure the hole is horizontal. 2. For intern

Page 9 - Not less than

172320Heating drainpointCyclone drainpointWall jigCondensatetrapHeating returnvalvesHeating flowvalveB DCA65 457058202Condensatedischarge pipe4.6 FIT

Page 10

184.7 REDUCING THE FLUE - Fig. 19When the flue length required is less than the minimum stated in Section 4.6, paragraph 1, refer to Fig. 19.Discard t

Page 11 - 3.6 BOILER LOCATION

19Alpha InTec S - Installation4.8 EXTENDING THE FLUE - Fig. 20Note: The flue assembly length must not exceed the maximum length stated, including the

Page 12

2Alpha InTec S - Benchmark SchemeBENCHMARK SCHEMETo comply with Building Regulations Part L1 (Part 6 in Scotland) the boiler should be installed in ac

Page 13 - 3.10 DISPOSAL OF CONDENSATE

20Alpha InTec S - Installation10. Secure the flue assembly to the bend with the clamp ensuring it is positioned centrally over the joint, ensuring the

Page 14 - Fig. 8 - External gully

21Alpha InTec S - InstallationPM length = C + (1 x 93° bend = 1.3 m) + (2 x 45° bends = 1.8 m)CMin.400 mmCD Easy-FlueFlue sealing collarTerminal end s

Page 15 - 4 INSTALLATION

224.10 CONNECT THE MAINS SUPPLY - Fig. 231. Gain access to the boiler terminal block by releasing the two fixing screws (one each side) securing the

Page 16

23Alpha InTec S - InstallationInTecBoilerDHW storage cylinderAlpha diverter valveAutomatic by-pass valveCylinder sensorHeating circuitABAB4.12 OPTION

Page 17 - Fig. 14 Fig. 15

24Alpha InTec S - Commissioning5 COMMISSIONINGFig. 26When commissioning the boiler, ensure the Benchmark Checklist is completed.5.1 FILL THE SYSTEM1

Page 18 - Check collar is sealing

255.4 INITIAL LIGHTING - Refer to Fig. 261. Before turning on the gas and electrical supplies check the heating system is filled to the correct press

Page 19 - Fig. 20 - Side flue

26Alpha InTec S - Commissioning5.6 CHECK THE BURNER PRESSURES AND COMBUSTION - Figs. 27, 28Press and hold in the reset button for eight seconds and t

Page 20

275.9 USER INFORMATIONThe User must be advised (and demonstrated if necessary) of the following important points:-1. How to light and turn off the b

Page 21 - Alpha InTec S - Installation

28Alpha InTec S - Routine Servicing6 ROUTINE SERVICINGTo ensure efficient operation of the boiler it is recommended that it is checked and serviced as

Page 22

29Fig. 296.2 PREPARE FOR SERVICING - Fig. 291. Ensure the electrical supply is isolated and the gas supply is off.2. Release the two screws securin

Page 23

3Alpha InTec S - Contents/IntroductionCONTENTS1 Introduction ...22 Technical data ...

Page 24 - 5 COMMISSIONING

30Alpha InTec S - Routine Servicing6.4 RE-ASSEMBLE THE BOILER1. Replace the burner, ensuring it is located correctly and secure it in position using

Page 25 - 5.5 BOILER OPERATION

31It is the law that any service work must be carried out by a competent person, i.e. Gas Safe registered personnel.Warning: Before replacing any boil

Page 26 - 5.8 FINAL ASSEMBLY

327.6 FAN - Fig. 291. Gain access behind the room sealed chamber as described in Section 7.1.2. Remove the two screws securing the air supply pipe

Page 27 - 5.10 INFORMATION MENU

337.10 GAS VALVE - Fig. 31Note: The replacement of the gas valve or PCB must be carried out by a Gas Safe registered engineer with the use of a flue

Page 28 - 6 ROUTINE SERVICING

34Alpha InTec S - Component Replacement7.15 CONDENSATE TRAP - Fig. 131. Gain access behind the front casing as described in Section 7.1.2. Disconne

Page 29 - Four nuts and washers and

35Alpha InTec S - Component Replacement7.21 AUTOMATIC AIR VENT - Fig. 341. Gain access behind the front casing and drain the boiler heating circuit

Page 30 - 6.4 RE-ASSEMBLE THE BOILER

36Alpha InTec S - Component Replacement7.25 EXPANSION VESSEL - Fig. 311. Gain access behind the front casing and drain the boiler heating circuit as

Page 31 - 7 COMPONENT REPLACEMENT

37Alpha InTec S - Wiring Diagrams8.1 ILLUSTRATED WIRING DIAGRAM8 WIRING DIAGRAMSGasValveBrGyBkWWOrOrRWBlOrBkRBr BlG/YRRBkWWGGRGyBlSparkGeneratorFlam

Page 32 - 7.6 FAN - Fig. 29

388.2 FUNCTIONAL FLOW WIRING DIAGRAMAlpha InTec S - Wiring DiagramsAlpha Control(Optional)12345PumpGas ValveFlowSensorSystem Pressure SwitchFuse 3.15

Page 33 - Spare fuse

39Alpha InTec S - Fault Finding9 ERROR CODES AND FAULT FINDING9.1 CARRY OUT INITIAL FAULT FINDING CHECKS1. Check that gas, electrical and water sup

Page 34 - Manual air vent

431.528.430.7287.23.02082N/A0.151.45362059.58.7272000.00390.688.92.50.51.03.08.01.01256Alpha InTec S - Technical Data2 TECHNICAL DATA2.1 TECHNICAL P

Page 35 - 7.22 PUMP - Refer to Fig. 34

40Alpha InTec S - Fault FindingErrorcodeFault Fault description Possible causesCheck flame sensing electrode and leadPCB faultCheck for jammed control

Page 36

41Alpha InTec S - Short Parts List10 SHORT PARTS LISTReferenceDescriptionBritish Gas GC No.Alpha Pt. No.Qty.1.0181621.0235513.0172811.0242961.0257971

Page 37 - 8 WIRING DIAGRAMS

This Commissioning Checklist is to be completed in full by the competent person who commissioned the boiler as a means of demonstratingcompliance with

Page 38

© Heating and Hotwater Industry Council (HHIC) www.centralheating.co.ukAll installations in England and wales must be notified to Local Authority Buil

Page 39

Manual compiled and designed by Publications 2000 - Tel: 01670 356211 09/13 D332These instructions have been carefully prepared but we reserve the ri

Page 40 - Alpha InTec S - Fault Finding

5Alpha InTec S - Technical Data2.3 PHYSICAL DATABoiler flow connections mmBoiler return connections mmRelief valve connection mmGas connectio

Page 41 - 10 SHORT PARTS LIST

6Alpha InTec S - Technical Data2.5 AVAILABLE PUMP HEAD FOR CENTRAL HEATINGFlow (litres/hr)Head (metres)200 600 1000 1400800 12001600400000.51.01.52.0

Page 42

72.7 BOILER SCHEMATICFig. 21 - Heat exchanger thermal fuse2 - Gas valve3 - Primary temperature sensor4 - Main burner5 - Primary/condensing

Page 43 - Service Provider

83.1 GAS SUPPLYThe meter and supply pipes must be capable of delivering the required quantity of gas in addition to the demand from any other applian

Page 44 - © Alpha Therm Limited 2013

9L = B + C + E + 245 mmAlpha InTec S - General Boiler InformationL = B + C + 245 mmCBECBEBFBCL = B + E + F + 245 mm + (90° bend = 1.3 metre)(add 45 mm